Debenhams Store, Southampton

Location: Southampton, Hampshire Client: Southampton Estates Ltd Value: £2,000,000 Timescale: September 2024 to October 2025 Scope: The asbestos removal, soft-strip, demolition and site clearance of the former department store. Project Background The project consisted of the demolition of the former Debenhams department store in the city centre of Southampton.  The existing building consisted of a [...]

Arrow Point, Horwich

Location: Horwich, Lancashire Client: Arrow Capital Partners Value: £1,750,000 Timescale: November 2024 to June 2025 Scope: The asbestos removal, soft-strip, demolition and site clearance of a former warehouses and supermarket. Project Background The project consisted of the demolition of a former 33,500m2 warehouse and a 6,000m2 Tesco store with an additional 20,000m2 of hardstanding to [...]

Daisyfield Pools Complex, Blackburn

Location: Blackburn, Lancashire Client: Blackburn with Darwen Borough Council Value: £200,000 Timescale: March 2025 to July 2025 Scope: The soft-strip, demolition and site remediation of a former swimming pool complex in Blackburn. Project Background The project involved the soft-strip and demolition of a former swimming pool complex in a residential area of Blackburn. Demolition Methodology [...]

St Joseph’s Seminary, West Lancashire

Location: Upholland, West Lancashire Client: Derwent Estates Value: £800,000 Timescale: Phase 1 : Feb 2023 to June 2023 / Phase 2 : May 2024 to Nov 2024 Scope: The careful demolition of part of the listed former seminary building. Project Background The grade II listed seminary building, first constructed in the 1880s, had laid empty [...]

House of Fraser Store, Birkenhead

Location: Birkenhead, Wirral Client: Wirral Growth Company Value: £425,000 Timescale: November 2023 to May 2024 Scope: The asbestos removal, soft-strip, demolition and site clearance of the former department store. Project Background The project consisted of the demolition of the former department store in the town centre of Birkenhead.  The existing building was brick built with [...]

Tarleton Academy, Lancashire

Location: Tarleton, Lancashire Client: Willmott Dixon Construction Value: £450,000 Timescale: June 2023 to October 2023 Scope: The asbestos removal, soft-strip, demolition and site clearance of old Tarleton Academy buildings. Project Background The project consisted of the demolition of a former secondary school on the same site as the new build Academy.  The demolition site was [...]

Marine Trading Estate, Leeds

Location: Stourton, Leeds Client: Baytree Logistics Properties Client's Project Manager: KAM Project Consultants Ltd Value: £1,100,000 Timescale: April 2022 to November 2022 Scope: The asbestos removal, soft-strip, demolition and site clearance of former offices and warehouses with extensive ground remediation. Project Background The project consisted of the demolition of a three-storey office block four large [...]

Century Mill, Bolton

Location: Bolton, Lancashire Client: Westchurch Homes Value: £500,000 Timescale: Phase 1 : January 2023 to June 2023 / Phase 2 : October 2024 to November 2024 Scope: The soft-strip demolition and site clearance of the former mill with 30m chimney. Project Background The project consisted of the demolition of the former 4-storey traditional brick built [...]

Moston Campus, Manchester College

Location: Moston, Manchester Client: OneManchester Client's Administrator: Arcus Consulting Value: £450,000 Timescale: November 2020 to July 2021 Scope: The asbestos removal, soft-strip, demolition and site clearance of the Moston Campus of Manchester College. Project Background The project consisted of the demolition of the Moston Campus of Manchester College.  The building was a 5-storey educational block [...]

Abraham Moss Leisure Centre

Location: Cheetham Hill, Manchester Client: Manchester City Council Client's Project Manager: Laing O'Rourke Construction Ltd Value: £750,000 Timescale: March 2021 to September 2021 Scope: The asbestos removal, soft-strip, demolition and site clearance of a former Leisure Centre and Library complex on a high school and primary school site. Project Background The project consisted of the [...]